This 500-ton cooling tower features a 1,500 gallon per minute (GPM) flow rate and is ideal for managing temperatures in industrial and commercial HVAC systems. Commonly used in manufacturing, oil refineries, chemical plants and thermal power stations, this cooling tower rental maintains optimal temperatures to ensure comfortable operating conditions. Manufacturers include brands like EVAPCO.
  • 500-ton cooling capacity
  • 460V/3PH
  • 1,500 gallon per minute flow rate
  • 8,370 lb. shipping weight
  • 24'2" length by 7'10" width by 10'6" height
  • Uses: Ideal for regulating indoor temperatures and ensure optimal working conditions for large industrial processes

Project spotlight

Rental Cooling Towers Rescue Plants When Failures Occur

Cooling tower

Summary

A mechanical contractor partnered with United Rentals to quickly install a temporary cooling tower system after a catastrophic weather event damaged an industrial facility's equipment, severely limiting production. Leveraging modular designs, custom engineering solutions, and streamlined services, United Rentals provided a safe, efficient, and tailored rental solution to bridge the gap caused by extended lead times for new equipment.

Challenge

The need to replace a failed cooling tower at an industrial facility was urgent, because production was being severely limited. Due to extended lead times for new equipment caused by supply chain issues and other hurdles, the contractor needed a temporary rental solution that could be quickly installed despite space limitations and complex installation requirements.

Impact

United Rentals successfully provided a temporary cooling tower system that enabled the industrial facility to quickly restore production capacity, despite challenges such as space limitations, complex installation requirements, and supply chain delays. This solution minimized operational downtime, ensured safety during installation and operation, and simplified administrative processes, allowing the facility to continue functioning efficiently while awaiting a permanent replacement.